Recent corporate announcements and filings for 532555

Business Update Positive
2026-11-06 15:10
Current scenario - Strong power demand growth in H1 FY27 with 11% generation growth and 15% demand growth YoY; October recorded 21% growth. - NTPC Group installed capacity reached 91,506 MW as of H1 FY27, with group generation at 236 billion units (up 10.4% YoY). - NGEL facing renewable energy curtailment due to transmission constraints, expected to resolve by mid-next year. - Coal plants achieved a PLF of 75.11% against the national average of 68.35%; captive coal dispatches grew 21% YoY to 26.13 MMT in H1. Management Guidance & Outlook - Revised RE capacity addition target for FY27 to around 8 GW (down from 8.8 GW) due to transmission delays. - Group capex for H1 FY27 stood at INR23,932 crores; ongoing construction capacity stands at over 17 GW (including 17.3 GW thermal). - Expanding into C&I segment (both renewable and thermal/heat solutions) and exploring BESS and pumped storage projects. - Declared first interim dividend of INR3 per share for FY27.
Business Update Positive
2026-11-06 12:06
- NTPC Limited has informed the stock exchanges about an update to its ESG rating by SES ESG Research Private Limited. - The rating agency has upgraded the company's ESG score from 64.2 to 64.6 based on the company's response and FY 2025-26 data.
Business Update Positive
2026-11-03 14:48
- NTPC Limited has received an ESG score of 64.2 from SES ESG Research Private Limited, an increase of 1.4 points YoY. - The ESG rating was conducted independently by the agency using publicly available information and was not commissioned by the company.
Business Update Neutral
2026-10-31 18:25
Concall Schedule Concall Date: 31 October 2026 Concall Time: Not Specified
Business Update Neutral
2026-10-31 15:11
- NTPC Limited has provided operational and financial snapshot for the quarter and half year ended 30 September 2026. - The detailed information has been made available on the company's official investor relations website link provided in the filing.
Financials Positive
2026-10-31 15:02
- NTPC Limited has fixed November 06, 2026, as the Record Date for the purpose of Dividend.
Financials Positive
2026-10-31 14:53
Q2 FY27 Consolidated Revenue ₹54,270Cr vs ₹44,784Cr (▲21% YoY) EBITDA ₹16,252Cr vs ₹13,394Cr (▲21% YoY) PAT ₹7,351Cr vs ₹5,225Cr (▲41% YoY) EBITDA Margin 29.9% vs 29.9% (▲4bps) Declared 1st Interim Dividend of ₹3 per share (30%); Record date is November 6, 2026
Financials Positive
2026-10-31 14:53
- NTPC Limited announced an interim dividend of ₹3 per equity share. - The decision was approved by the Board of Directors at their meeting held on October 31, 2026.
Business Update Positive
2026-10-30 12:36
- NTPC Limited announced the commercial operation of the fifth part capacity of 95.6 MW of the Kalasar Solar Energy Project in Bikaner, Rajasthan. - This project is part of the 650 MW Solar component under the 500 MW REMCL RTC Project of NTPC Renewable Energy Limited. - With this addition, the total installed capacity of the NTPC group stands at 91,668 MW and commercial capacity at 90,588 MW.
Business Update Positive
2026-10-29 18:24
Order Win: NTPC subsidiary NVVN declared its first BESS Project (250 MW / 500 MWh) commercial Completion Timeline: Commercial operation commenced on 27th October 2026 and power scheduling began on 28th October 2026.
Business Update Neutral
2026-10-28 18:25
Concall Schedule Concall Date: 31 October 2026 Concall Time: Not specified (Refer to company website for details) Agenda: Discuss results for the quarter and half year ended 30 September 2026
Governance Neutral
2026-10-23 17:24
- Appointment of Shri Diwakar Nath Misra as Government Nominee Director (Non-Executive) on the Board of NTPC Limited effective October 23, 2026. - Shri Diwakar Nath Misra is a 2000 batch IAS officer (Assam-Meghalaya cadre) and currently serves as Additional Secretary, Ministry of Power, Government of India. - Confirmed that he is not debarred from holding the office of Director by SEBI or any other authority and does not hold any shares in the company.
Routine Neutral
2026-10-20 18:37
- NTPC Limited has issued a clarification regarding a news article published on the website of AD HOC NEWS titled "NTPC Posts 7.43 Percent Profit Growth; Buyback Sets Date for NTPC stock". - The company has stated that the information contained in the article is factually incorrect and misleading. - The statements do not correspond with any official disclosures made by the company to the stock exchanges. - Investors are advised to rely only on official company filings. - The company is taking up the matter with the publisher for corrective action.
Governance Neutral
2026-10-19 16:22
- NTPC Limited announced the appointment of Shri Diwakar Nath Misra, Additional Secretary, Ministry of Power, as Government Nominee Director on the Board of the Company. - The appointment is effective from 19th October 2026, lasting until his tenure in the Ministry of Power or until further orders.
Business Update Positive
2026-10-15 18:24
NTPC Limited has signed a Cooperation Agreement with Africa50 to jointly develop power-generation projects and cross-border electricity trading opportunities across Africa. - The partnership combines NTPC's technical and operational expertise with Africa50's project development and financing capabilities. - The collaboration aims to advance commercially viable power projects and expand reliable electricity supply across African countries.
Business Update Positive
2026-10-10 19:35
- NTPC Limited announced the commercial operation of the fourth part capacity of 66.18 MW of the Kalasar Solar Energy Project in Bikaner, Rajasthan. - This capacity is part of the 650 MW solar component under the 500 MW REMCL RTC Project of NTPC Renewable Energy Limited. - With this addition, the total installed and commercial capacity of the NTPC group stands at 91,572 MW and 90,492 MW respectively.
Governance Neutral
2026-10-05 20:47
- Shri Piyush Singh ceased to be the Government Nominee Director of NTPC Limited with effect from October 05, 2026. - Cessation is due to his relieving from duties in the Ministry of Power. - Intimation made pursuant to Regulation 30 of SEBI (LODR) Regulations, 2015.
Business Update Positive
2026-10-01 15:34
- NTPC Green Energy Limited (NGEL) declared commercial operation of the fourth part capacity of 50 MW solar capacity out of a 300 MW solar component. - The project is part of a 200 MW RE Round The Clock (RTC) project in Rajasthan. - Commercial operation is effective from 00:00 hrs of 2nd October 2026. - Total installed capacity of the NTPC group now stands at 91,506 MW and commercial capacity at 90,426 MW.
Governance Neutral
2026-09-30 13:38
- NTPC Limited announced the cessation of senior management personnel due to superannuation. - Shri Chandan Kumar Samanta, Executive Director, superannuates on 30th September 2026. - Other senior management changes were also intimated pursuant to Regulation 30 of SEBI LODR Regulations.
Business Update Positive
2026-09-30 13:09
- NTPC Renewable Energy Limited declared the commercial operation of the second (73.06 MW) and third (80.88 MW) parts of the Kalasar Solar Energy Project in Bikaner, Rajasthan, effective October 1, 2026. - Total installed capacity of the NTPC group stands at 91,456 MW and commercial capacity at 90,376 MW.
Business Update Positive
2026-09-26 19:30
- NTPC Limited announced the commercial operation of the first part capacity of 81.34 MW of the Kalasar Solar Energy Project at Bikaner, Rajasthan. - This project is part of a 650 MW solar component under the 500 MW REMCL RTC Project of NTPC Renewable Energy Limited. - With this addition, the total installed and commercial capacity of the NTPC group reached 91,302 MW and 90,222 MW respectively.
Ownership Neutral
2026-09-22 17:17
- NTPC announced the closure of the trading window for insiders. - The trading window will remain closed from October 1, 2026, until 48 hours after the declaration of financial results for the quarter ending September 30, 2026.
Business Update Positive
2026-09-22 13:14
- NTPC has received an ESG rating of "Crisil ESG 62 [Category: Strong]" from CRISIL ESG Ratings & Analytics Limited. The rating was prepared independently by CRISIL based on publicly available information.
Routine Neutral
2026-09-22 13:08
New Filing detected. See link for details.
Business Update Positive
2026-09-19 12:42
- NTPC Limited announced the declaration of commercial operation for two renewable energy projects by its subsidiary NTPC Green Energy Limited. - 68.22 MW third part capacity of Gujarat Solar PV Project at Dahod became operational w.e.f. July 23, 2026. - 9.45 MW third part capacity of Vanki Wind Energy Project in Nakhatrana, Kutch, Gujarat became operational w.e.f. September 19, 2026. - With these additions, the total installed capacity of the NTPC group stands at 91,164 MW and commercial capacity at 90,084 MW. - The total installed capacity of NTPC Green Energy Limited group increased to 10,920.53 MW.
Governance Neutral
2026-09-18 19:32
- NTPC Limited announced the appointment of Joint Statutory Auditors by C&AG for the Financial Year 2026-27. - The appointment date is 18th September 2026. - The appointed firms are M/s. HEM SANDEEP & Co., M/s. OP Bagla & Co., M/s. Laxminiwas & Co., M/s. PSD & Associates, and M/s. Laldash & Co.
Business Update Positive
2026-09-18 14:44
- NTPC received an independent ESG rating of "61 i.e. Performer" from Niche Ninety Nine Capability and Certifications (OPC) Private Limited, a SEBI registered rating provider.
Business Update Positive
2026-09-12 17:02
- NTPC's stepdown subsidiary, NTPC Renewable Energy Limited, achieved Commercial Operation Declaration (COD) for the second part capacity of 6.3 MW of the Vanki Wind Energy Project, effective September 13, 2026. - With this addition, the total installed capacity of the NTPC group now stands at 91,086 MW, and commercial capacity at 90,006 MW.
Governance Neutral
2026-09-08 14:42
- NTPC announced the appointment of 5 Statutory/Joint Statutory Auditors by C&AG for Financial Year 2026-27. - The appointed firms include M/s HEM SANDEEP & CO, M/s O P BAGLA & CO, LLP, M/s LAXMINIWAS & CO, M/s PSD & ASSOCIATES, and M/s LALDASH & CO.
Business Update Neutral
2026-09-03 14:49
- NTPC Limited received an ESG rating/score of "49" (Category: Adequate) from ESG Risk Assessments and Insights Limited. - The rating was prepared independently by the agency based on public domain information, not commissioned by NTPC.
Governance Neutral
2026-08-31 13:04
- Intimation of cessation of four Senior Management personnel (Ms. Renu Narang, Ms. Rachana Singh Bhal, Shri E Satya Phani Kumar, Shri Dilip Kaibortta). - The cessation is due to superannuation. - Effective date: 31st August 2026.
Governance Negative
2026-08-26 13:44
CRITICAL RED FLAG DETECTED
- BSE and NSE have imposed a fine of ₹5,36,900 each on NTPC for non-compliance with Regulation 17(1) of Listing Regulations (Board composition) for the quarter ended June 30, 2026. - NTPC has requested to waive the fines, stating that director appointments for the Government Company vest with the President of India. - The company is pursuing the appointment of requisite Independent Directors with the Ministry of Power.
Business Update Positive
2026-08-04 18:58
- NTPC Limited filed its Business Responsibility and Sustainability Report for FY 2025-26. - The company reported zero confirmed bribery and corruption cases in FY 2025-26. - Key targets include 60 GW renewable energy capacity by 2032, 12% reduction in energy intensity, and 34% reduction in specific water consumption by FY 2032. - All stakeholder complaints were resolved within the financial year, with 0 pending. Investor grievances significantly reduced.
Financials Positive
2026-08-04 18:48
- Notice of 50th AGM on August 27, 2026, at 10:30 AM (IST). E-voting is from Aug 24-26, 2026. - Integrated Annual Report 2025-26 highlights FY26 EBITDA ₹60,564 Cr and PAT ₹27,546 Cr. - NTPC targets 60 GW renewable energy by 2032, alongside nuclear expansion, supporting Viksit Bharat and Net Zero goals.
Routine Neutral
2026-08-02 15:21
New Filing detected. See link for details.
Governance Neutral
2026-07-31 10:46
- Shri Ram Bhajan Malik, Executive Director (Senior Management) of NTPC Limited, will cease to be in the role. - The cessation is due to superannuation and will be effective from 31st July 2026.
Business Update Positive
2026-07-29 19:07
- NTPC's subsidiary, NTPC Green Energy Limited (NGEL), declared commercial operation (COD) of 50 MW Solar Capacity, part of a 100 MW RE Round The Clock (RTC) project in Rajasthan, effective 31st July 2026. - With this addition, the total installed capacity of the NTPC group stands at 91,080 MW, with commercial capacity at 90,000 MW. - The total installed capacity of the NGEL group increases to 10,836.56 MW.
Governance Positive
2026-07-28 17:21
- The President of India has extended the re-employment period of Shri Gurdeep Singh as the Chairman & Managing Director of NTPC Limited. - The extension is on a contract basis for a further period of six months, effective from August 1, 2026. - This is until the regular incumbent assumes charge or until further orders.
Business Update Neutral
2026-07-27 19:14
- Audio recording of the 22nd Annual Analysts and Institutional Investors Meet held on 27th July 2026 is now available. - The link for accessing the recording is provided on the company's website.
Governance Positive
2026-07-27 18:45
- The 50th Annual General Meeting (AGM) will be held on Thursday, August 27, 2026, at 10:30 a.m. via Video Conferencing (VC)/Other Audio-Visual Means (OAVM). - The record date for the final dividend of ₹3.50 per share for the Financial Year 2025-26 is fixed for Wednesday, September 2, 2026. - Payment of the final dividend will be made on or after September 23, 2026, subject to approval at the AGM.
Governance Positive
2026-07-27 18:39
- Intimation of 50th Annual General Meeting (AGM) to be held on Thursday, 27th August 2026 at 10:30 a.m. via Video Conferencing (VC)/Other Audio-Visual Means (OAVM). - Record Date for the final dividend (FY 2025-26) of ₹3.50 per share (on a face value of ₹10) is Wednesday, 2nd September 2026. - Dividend payment, subject to AGM approval, will be made on or after 23rd September 2026.
Business Update Neutral
2026-07-24 20:19
- The Operational & Financial Snapshot for the quarter ended June 30, 2026, is available on the company's investor relations link, which covers conference calls, analyst meets, and investor interactions.
Governance Positive
2026-07-24 20:00
- Board of Directors approved raising funds up to ₹12,000 Crore through the issue of Non-Convertible Debentures (NCDs). - The NCDs will be issued via private placement in one or more tranches/series. - The approval was given at the meeting held on 24th July 2026.
Financials Positive
2026-07-24 19:45
- Consolidated Revenue ₹50,740.96Cr vs ₹47,064.35Cr (▲7.8% YoY) - EBITDA ₹16,230.59Cr vs ₹12,578.93Cr (▲29.0% YoY) - PAT ₹6,896.44Cr vs ₹6,108.46Cr (▲12.9% YoY) - EBITDA Margin 32.0% vs 26.7% (▲526bps)
Business Update Positive
2026-07-24 12:16
- NTPC's subsidiary, NTPC Green Energy Limited (NGEL), declared Commercial Operation (COD) for the first part capacity of 64.76 MW out of 225 MW Khavda Solar PV Project in Gujarat, effective July 24, 2026. - This addition increases the total installed capacity of the NTPC Group to 91,030 MW and commercial capacity to 89,950 MW.
Business Update Neutral
2026-07-22 10:28
- Concall Schedule: 22nd Annual Analysts and Institutional Investors Meet - Concall Date: 27 July 2026
Governance Neutral
2026-07-18 22:30
- NTPC Limited announced the appointment of Dr. Som Nath Sachdeva as an Additional Director (Independent Director). - The appointment is for a period of three years, effective from 18th July 2026.
Business Update Positive
2026-07-17 22:30
- NTPC's subsidiary THDC India Limited declared its 11 MWac Floating Solar Plant at Khurja STPP on commercial operation from July 17, 2026. - This increases the NTPC group's total installed capacity to 90,965 MW and commercial capacity to 89,885 MW.
Governance Neutral
2026-07-17 18:20
- Board meeting scheduled for July 24, 2026, to consider un-audited financial results for the quarter ended June 30, 2026. - The board will also consider raising funds up to ₹12,000 Crore via Non-Convertible Debentures. - Trading window for transactions in company securities is closed from July 1, 2026, to July 26, 2026.
Governance Neutral
2026-07-17 18:05
- NTPC Limited announced the appointment of Dr. Som Nath Sachdeva as a Non-Official Independent Director on its Board for a period of three years, effective from July 17, 2026.
Business Update Positive
2026-07-11 17:58
- NTPC Limited's Board of Directors approved an investment proposal for the Lara Super Thermal Power Project, Stage-III (2x800 MW). - The estimated cost for this project is ₹20,456.70 Crore.
Business Update Positive
2026-07-08 14:25
- NTPC Green Energy Limited (a subsidiary) declared commercial operation of the first part capacity of 50.4 MW of Vanki Wind Energy Project in Gujarat. - The project by NTPC Renewable Energy Limited (a step-down subsidiary) is effective from July 8, 2026. - With this, the total installed capacity of the NTPC Group stands at 90,954 MW and commercial capacity at 89,874 MW. - NTPC Green Energy Limited Group's total installed capacity increased to 10,721.80 MW.
Business Update Positive
2026-06-30 21:41
- NTPC's JV, NSPCL, declared commercial operation of the final 5 MW (Island-2) of Bhilai Floating Solar Power Station on June 24, 2026. - The entire 15 MW Floating Solar Power Station is now commercially operational. - Total installed capacity of NTPC group reached 90,904 MW and commercial capacity 89,824 MW.
Business Update Positive
2026-06-30 12:53
- NTPC declared the commercial operation of the third and last part capacity of 41.6 MW out of its 176 MW Solar PV Project at Ramagundam, Telangana, effective June 30, 2026. - This completes the full 176 MW capacity of the project. - With this, the total installed capacity of the NTPC group stands at 90,899 MW and commercial capacity at 89,819 MW.
Governance Neutral
2026-06-30 12:02
- Intimation of change in Senior Management at NTPC Limited.- Shri Sanjay Kumar Sinha (Executive Director) has ceased.- Shri Jagadish Chandra Sastry Bhamidipati and Shri Jayadev Parida (Executive Directors) have superannuated on June 30, 2026.
Business Update Positive
2026-06-26 15:08
- NTPC Limited incorporated 'NTPC (Mauritius) Energy Limited' as a wholly-owned subsidiary on June 26, 2026. - The subsidiary, capitalized at MUR 1 Million (INR 19.80 Lacs), will develop Floating Solar PV and Battery Energy Storage projects in Mauritius.
Routine Neutral
2026-06-23 16:54
- Trading Window for dealing in the company's securities will remain closed from July 1, 2026. - The window will reopen 48 hours after the declaration of Financial Results for the quarter ending June 30, 2026. - This closure is as per SEBI (Prohibition of Insider Trading) Regulations, 2015.
Business Update Positive
2026-06-23 16:29
- Unit#2 (800 MW) of Patratu STPP, Phase-1 (3x800MW) of Patratu Vidyut Utpadan Nigam Limited (PVUNL), a subsidiary of NTPC Limited, is declared on Commercial Operation w.e.f. 25th June 2026. - Total installed capacity of NTPC group now stands at 90,857 MW. - Commercial capacity now stands at 89,777 MW.
Business Update Positive
2026-06-12 21:23
- NTPC's subsidiary, NTPC Green Energy Limited (NGEL), declared Commercial Operation (COD) of 50 MW Solar Capacity (part of 200 MW RE RTC project) in Rajasthan, effective June 14, 2026. - Post this, NTPC group's total installed capacity stands at 90,857 MW and NGEL Group's at 10,671.40 MW.
Governance Neutral
2026-06-08 21:50
- NTPC Limited announced the appointment of 34 officials as Executive Director (Senior Management). - The appointments are effective from June 8, 2026.
Business Update Positive
2026-06-04 21:53
- NTPC Limited and UPRVUNL signed a Supplementary Joint Venture Agreement (SJVA)-III for their 50:50 JV, Meja Urja Nigam Private Limited (MUNPL). - The agreement enhances the capacity of Meja Stage-II from 2x660 MW to 3x800 MW. - Signed on June 4, 2026.
Governance Neutral
2026-05-29 11:59
NTPC Limited announced the cessation of Shri S K Suar, Executive Director (Senior Management), due to superannuation, effective May 31, 2026.
Business Update Positive
2026-05-29 11:46
NTPC Limited announced the declaration of commercial operation for the second part capacity of 34.4 MW out of its 176 MW Solar PV Project at Ramagundam, Telangana, effective May 29, 2026. This adds to NTPC's operational capacity, bringing the total installed capacity of the NTPC group to 90,807 MW and commercial capacity to 88,927 MW.
Governance Negative
2026-05-27 23:15
CRITICAL RED FLAG DETECTED
NTPC Limited received fines of ₹5,31,000 each from BSE and NSE for non-compliance with Regulation 17(1) of Listing Regulations for the quarter ended March 31, 2026. The non-compliance relates to the appointment of Independent Directors. NTPC stated that as a Government Company, director appointments vest with the President of India and they are pursuing the matter with the Ministry of Power for requisite appointments.
Business Update Positive
2026-05-27 23:10
NTPC's subsidiary, NTPC Green Energy Limited (NGEL), announced the Commercial Operation Date (COD) for the final 105 MW capacity of the 1200 MW Khavda-II Solar PV Project in Gujarat, effective May 28, 2026. With this commissioning, the NTPC Group's total installed capacity now stands at 90,773 MW, and commercial capacity at 88,893 MW. NGEL's total installed capacity increased to 10,621.40 MW.
Business Update Positive
2026-05-27 18:01
NTPC Group plans significant capacity additions of approximately 9.56 GW in FY27, 10.04 GW in FY28, and 11.48 GW in FY29, with a strong focus on renewable energy, including an average 8 GW addition annually for NGEL towards its 60 GW target by 2032. NGEL's projected capex is INR35,800 Cr in FY27 and INR46,000 Cr in FY28. The company is developing nuclear projects, with Mahi Banswara aiming for first concrete pour by August 2027 and unit synchronization by November 2032. To enhance grid stability and renewable integration, 5 GWh BESS capacity is being executed at thermal plants and 1,320 MW batteries for renewable projects. Management noted that despite lower thermal generation due to RE injection, fixed charges compensation and regulatory support protect profitability and return on equity.
Business Update Neutral
2026-05-23 18:25
NTPC Ltd. held a conference call on May 23, 2026, to discuss its financial results for the quarter and year ended March 31, 2026, with analysts and investors. An audio recording of the conference call is available via the provided link.
Business Update Neutral
2026-05-23 15:31
NTPC Limited announced the availability of its Operational & Financial Snapshot for the quarter and year ended March 31, 2026. This information, along with details for the conference call, analyst meet, and investor interactions, can be accessed via the link provided on its investor relations page.
Governance Neutral
2026-05-23 15:28
NTPC Limited announced the appointment of Shri Sudhiranjan Mohini as the Head of Internal Audit (Senior Management), effective May 23, 2026. The appointment was approved by the Board of Directors on the same date for a term of 6.1 years or until further order. Shri Mohini has over 27 years of experience in finance, accounts, and audit.
Financials Positive
2026-05-23 15:19
NTPC Limited reported Standalone Revenue of ₹43,110.74 Cr for Q4 FY26, a slight decrease of 1.81% YoY from ₹43,903.65 Cr in Q4 FY25. However, EBITDA grew significantly by 11.09% YoY to ₹12,504.12 Cr compared to ₹11,255.03 Cr. Net Profit (PAT) showed a strong increase of 51.38% YoY, reaching ₹8,747.27 Cr from ₹5,778.14 Cr. The EBITDA Margin expanded by 335 bps, from 25.64% to 28.99%. The Board also recommended a final dividend of ₹3.50 per share for FY2025-26, bringing the total dividend for the year to ₹9.00 per share.
Financials Positive
2026-05-23 15:17
NTPC Limited reported its consolidated financial results for Q4 FY26. Consolidated Revenue stood at ₹49,687.77 Cr compared to ₹49,833.70 Cr (▼0.29% YoY). EBITDA was ₹16,514.18 Cr against ₹15,386.56 Cr (▲7.32% YoY), and Net Profit (PAT) increased significantly to ₹10,614.95 Cr from ₹7,897.14 Cr (▲34.41% YoY). The EBITDA Margin expanded to 33.23% from 30.87% (▲236bps). The Board also recommended a final dividend of ₹3.50 per share for FY26, bringing the total dividend for the year to ₹9.00 per share.
Governance Negative
2026-05-19 19:07
CRITICAL RED FLAG DETECTED
NTPC Limited announced that Shri R Sarangapani, Executive Director (Senior Management), has been relieved from the company's services effective May 19, 2026, following the acceptance of his pre-mature retirement application.
Business Update Neutral
2026-05-19 15:25
NTPC Ltd. will host a conference call on May 23, 2026, where the Senior Management team will discuss the company's results for the quarter and year ended March 31, 2026, and interact with analysts and investors.
Business Update Positive
2026-05-18 13:52
NTPC Limited's subsidiary, Patratu Vidyut Utpadan Nigam Limited (PVUNL), has successfully completed the trial operation of its 800 MW Unit-2. This unit is now included in NTPC's installed capacity, bringing the total installed capacity of the NTPC group to 90,668 MW.
Governance Positive
2026-05-15 16:14
NTPC Limited announced that a Board Meeting will be held on May 23, 2026, to consider and approve the Annual Standalone and Consolidated Financial Statements for the financial year ended March 31, 2026, and to recommend a final dividend for FY26. The trading window remains closed from April 1, 2026, until May 25, 2026.
Business Update Positive
2026-05-14 16:04
NTPC's subsidiary, NTPC Green Energy Limited (NGEL), declared commercial operation for new solar project capacities in Rajasthan, effective May 15, 2026. This includes 12.5 MW from a 150 MW solar project and 50 MW from a 300 MW solar project. With these additions, NGEL Group's total installed capacity increases to 10,516.40 MW, and the NTPC group's total installed capacity stands at 89,868 MW, with commercial capacity at 88,788 MW.
Business Update Positive
2026-05-07 18:04
NTPC Limited has signed a Termination Agreement on May 7, 2026, to acquire the Municipal Corporation of Delhi's (MCD) remaining 26% equity stake (52,000 shares for Rs. 5,20,000) in NTPC EDMC Waste Solutions Private Limited (NEWS). This acquisition will make NEWS a wholly-owned subsidiary of NTPC, consolidating its 'Waste to Wealth' business. The acquisition is expected to complete by Q1 FY26-27.
Business Update Positive
2026-05-02 10:51
NTPC Limited announced the declaration of commercial operation for 100 MW out of 176 MW capacity of its Solar PV Project at Ramagundam, Telangana, effective May 2, 2026. With this commissioning, the total installed capacity of the NTPC group stands at 89,805 MW and commercial capacity at 88,725 MW.
Governance Neutral
2026-04-30 13:14
NTPC Limited announced the cessation of Shri Kariveda Narasimha Reddy as Executive Director and Shri Anuj Kush as Chief General Manager due to superannuation, effective April 30, 2026.
Business Update Neutral
2026-04-27 18:17
NTPC clarified a market rumour about exploring 2 nuclear power units in Bihar. The company stated it has not commenced feasibility studies, and current exploration activities are preliminary and exploratory, not constituting a material event under SEBI (LODR) Regulations.
Business Update Positive
2026-04-24 17:46
NTPC Green Energy Limited declared Commercial Operation of 90 MW (seventh part capacity) of the Khavda-II Solar PV Project in Gujarat, effective April 25, 2026. This increases the total installed capacity of NTPC Green Energy Limited Group to 10,453.90 MW.
Routine Neutral
2026-04-17 22:49
New Filing detected. See link for details.
Business Update Positive
2026-04-17 11:18
NTPC Green Energy Limited (NGEL), a subsidiary, declared commercial operation (COD) of a 150 MW solar project in Rajasthan effective April 18, 2026. This addition increases the NTPC Group's total installed capacity to 89,528 MW and NGEL's installed capacity to 10,276.40 MW.
Governance Neutral
2026-04-16 10:56
CRITICAL RED FLAG DETECTED
NTPC Limited announced that Shri Anil Kumar Trigunayat (DIN: 07900294) ceased to be an Independent Director upon completion of his tenure on April 15, 2026, as per a Ministry of Power order dated April 16, 2025.
Business Update Positive
2026-04-11 13:38
NTPC's subsidiary, THDC India Limited, declared the 4th Unit (250 MW) of Tehri PSP commercially operational from April 12, 2026. This increases NTPC group's total installed capacity to 89,378 MW and commercial capacity to 88,298 MW.
Business Update Positive
2026-04-10 11:12
NTPC received an ESG rating of 74.3 (Leadership category) from CARE ESG Ratings Limited. Pillar-wise scores are Environment 62.7, Social 84.0, and Governance 83.6, reflecting strong overall performance.
Routine Neutral
2026-04-08 18:03
New Filing detected. See link for details.
Routine Neutral
2026-04-08 17:47
New Filing detected. See link for details.
Routine Neutral
2026-04-07 14:38
NTPC Limited submitted a Certificate under Regulation 74(5) of SEBI (Depositories and Participants) Regulations, 2018, for the quarter ended March 31, 2026. It confirms that securities received for dematerialization were processed and listed, and physical certificates were duly cancelled.
Business Update Neutral
2026-04-01 19:07
NTPC clarified its disclosure dated April 1, 2026, stating the group's total installed capacity is 89,108 MW and commercial capacity is 88,028 MW.
Business Update Positive
2026-04-01 15:18
NTPC announced the completion of the phased transfer of its coal mining business, including Pakri Barwadih Coal Mine and CMHQ, to its wholly-owned subsidiary, NTPC Mining Limited, effective April 1, 2026. Commercial operation of Pakri Barwadih North West Coal Mining Project also declared w.e.f. April 1, 2026.
Business Update Neutral
2026-04-01 13:18
NTPC Limited completed the transfer of Pakri Barwadih Coal Mine and Coal Mining Head Quarter to its wholly-owned subsidiary, NTPC Mining Limited (NML), effective April 1, 2026. This marks the successful completion of the hiving-off of NTPC's coal mining business.
Routine Neutral
2026-04-01 11:03
New Filing detected. See link for details.
Business Update Positive
2026-03-31 10:50
NTPC Green Energy Ltd, a subsidiary of NTPC, declared commercial operation of 78.02 MW (Khavda-I) and 90 MW (Khavda-II) Solar PV Projects in Gujarat, effective March 31, 2026. This increases the total installed capacity of NTPC Green Energy Group to 10,075.70 MW and NTPC Group to 89,057 MW.
Governance Neutral
2026-03-30 15:55
NTPC Limited informed about the cessation of Shri Arindam Sinha, Regional Executive Director, due to superannuation, effective March 31, 2026.
Business Update Positive
2026-03-28 22:21
NTPC's subsidiary, NTPC Green Energy, declared commercial operation for 75 MW from Bhadla Solar PV Project (Rajasthan) on March 25, 2026, and 105 MW from Khavda-II Solar PV Project (Gujarat) on March 29, 2026. This increases the NTPC group's total installed capacity to 88,889 MW.
Business Update Positive
2026-03-28 13:07
NTPC's Board approved a ₹5,821.90 Cr investment for a 4.70 GWh Battery Energy Storage System (BESS) and an additional ₹3,173.67 Cr equity commitment in its JV, MUNPL, for Meja Super Thermal Power Project Stage-II (3x800 MW) expansion.
Business Update Positive
2026-03-28 13:06
NTPC's Board on March 28, 2026, approved a ₹5,821.90 Cr investment for a 4.70 GWh Battery Energy Storage System and an additional ₹3,173.67 Cr equity commitment for Meja Super Thermal Power Project Stage-II (3x800 MW) expansion via MUNPL.
Business Update Positive
2026-03-26 11:51
NTPC's ESG rating was upgraded by MSCI ESG Ratings from B to BB, effective March 23, 2026. This marks a significant improvement and the second upgrade this financial year, reflecting enhanced sustainability and governance.
Business Update Neutral
2026-03-24 13:43
NTPC Limited received an ESG rating of "54" (Category: Adequate) from ESG Risk Assessments & Insights Limited, based on publicly available data for FY 2024-25. The company did not engage the rating provider for this independent assessment.